Hygienic handover grid

Ten things to inspect, measure and sign before you accept a yogurt, cheese or butter line. Tick what your supplier has already evidenced and the grid tells you what is still open. Take it to any supplier you are talking to, including us.

SignedWhat to checkHow it is measuredEvidence to keep
Floor fall to drain Spirit level or laser across the wet area, drain to high point Measured fall recorded on the layout drawing
Internal corner radius on product contact parts Radius gauge on vessel corners and welds Gauge photograph against each vessel serial number
Weld finish inside product vessels Visual inspection plus surface roughness reading Roughness readings listed per vessel
Spray device coverage inside vessels Riboflavin trace under ultraviolet light after a wash cycle Before and after photographs of every vessel interior
Cleaning chemical concentration Conductivity or titration at the return line during a cycle Cycle log showing concentration against set point
Cleaning temperature and hold time Return-line probe logged for the full cycle Printed or exported cycle chart
Pasteurisation hold and diversion Timed hold check and a forced diversion test Diversion test sheet with the recorded temperature
Drainability of pipe runs Visual check for pooling after a full drain-down Photographs of the low points after drain-down
Trial production against your own recipe Full run at rate with your milk and your pack format Output weights, pack samples and the run record
Documentation pack handed over Line-by-line check against the contract deliverables list Signed index of drawings, manuals and certificates