Ten things to inspect, measure and sign before you accept a yogurt, cheese or butter line. Tick what your supplier has already evidenced and the grid tells you what is still open. Take it to any supplier you are talking to, including us.
| Signed | What to check | How it is measured | Evidence to keep |
|---|---|---|---|
| Floor fall to drain | Spirit level or laser across the wet area, drain to high point | Measured fall recorded on the layout drawing | |
| Internal corner radius on product contact parts | Radius gauge on vessel corners and welds | Gauge photograph against each vessel serial number | |
| Weld finish inside product vessels | Visual inspection plus surface roughness reading | Roughness readings listed per vessel | |
| Spray device coverage inside vessels | Riboflavin trace under ultraviolet light after a wash cycle | Before and after photographs of every vessel interior | |
| Cleaning chemical concentration | Conductivity or titration at the return line during a cycle | Cycle log showing concentration against set point | |
| Cleaning temperature and hold time | Return-line probe logged for the full cycle | Printed or exported cycle chart | |
| Pasteurisation hold and diversion | Timed hold check and a forced diversion test | Diversion test sheet with the recorded temperature | |
| Drainability of pipe runs | Visual check for pooling after a full drain-down | Photographs of the low points after drain-down | |
| Trial production against your own recipe | Full run at rate with your milk and your pack format | Output weights, pack samples and the run record | |
| Documentation pack handed over | Line-by-line check against the contract deliverables list | Signed index of drawings, manuals and certificates |