Site and Utility Checklist

These are the nine categories that decide whether a freeze drying and quick freezing line fits your building. Settle them with your facilities engineer before you ask anyone for a price, because every unanswered line here turns into a variation order later.

0 of 9 categories settled ·
CategoryWhat to establishWhere our figure comes from
Installed electrical load Spare capacity at the board, and whether a transformer upgrade is needed FDG-5 22.5 kW, FDG-10 34 kW, FDG-20 73 kW; FDG-30 confirmed with the quotation
Refrigeration capacity Whether you add a package or extend an existing plant room FDG-5 8 kW, FDG-10 15 kW, FDG-20 28 kW, FDG-30 42 kW; add the freezer load separately
Cooling water Flow rate, supply temperature and whether a tower or chiller already exists A water tank is required from FDG-10 upward; flow and temperature in the technical annex
Compressed air Pressure, quality class and dryer capacity for pneumatic valves and the packing station Confirmed in the technical annex with your quotation
Drainage Floor gullies for defrost and washdown water, and the discharge route Confirmed in the technical annex with your quotation
Floor loading Slab capacity under the chamber and under loaded trolleys in transit Confirmed in the technical annex with your quotation
Footprint and access Machine envelope plus service access, and the route in through the building FDG-5 3800 × 1100 × 1600 mm to FDG-30 4500 × 2155 × 2605 mm; tunnel freezer up to 19.2 m long, spiral up to 4 m high
Clear height Height under services, especially for a spiral freezer Confirmed in the technical annex with your quotation
Ambient temperature and humidity Room conditions at the unloading point, where dried product picks moisture back up fastest Confirmed in the technical annex with your quotation

Where our scope ends and yours begins

  • We supply the equipment, layout and pipe-routing guidance, mechanical and electrical installation support, interlocked process commissioning, freeze drying curve optimisation and operator training.
  • Building services up to our terminal points — power, water, air, drainage and the floor itself — remain on your scope.
  • The boundary is written into the technical annex so that neither side discovers it during commissioning.